Concept explainers
Analyze manufacturing
Smith Foundry in Columbus, Ohio, uses a predetermined manufacturing overhead rate to allocate overhead to individual jobs based on the machine hours required. At the beginning of the year, the company expected to incur the following:
$ 630,000 | |
Direct labor cost | $1,650,000 |
Machine hours | 90,000 |
At the end of the year, the company had actually incurred the following:
Direct labor cost | $1,230,000 |
Depreciation on manufacturing plant and equipment | $ 480,000 |
Property taxes on plant | $ 19,500 |
Sales salaries | $ 26,500 |
Delivery drivers’ wages | $ 17,000 |
Plant janitors’ wages | $ 8,500 |
Machine hours | 56,500 hours |
Requirements
- 1. Compute Smith’s predetermined manufacturing overhead rate.
- 2. How much manufacturing overhead was allocated to jobs during the year?
- 3. How much manufacturing overhead was incurred during the year? Is manufacturing overhead underallocated or overallocated at the end of the year? By how much?
- 4. Were the jobs overcosted or undercosted? By how much?
Trending nowThis is a popular solution!
Chapter 3 Solutions
Managerial Accounting (5th Edition)
Additional Business Textbook Solutions
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
Cost Accounting (15th Edition)
Horngren's Accounting (11th Edition)
Financial Accounting (11th Edition)
Financial Accounting, Student Value Edition (5th Edition)
Horngren's Financial & Managerial Accounting, The Managerial Chapters (6th Edition)
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardIn Class Assignment 1 AlSaleh has assigned overhead on a plantwide basis to its two products (Tables and Chairs) using direct labor hours which are estimated to be 200,000 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are Ordering and receiving (cost driver is Purchase orders) and machine setup (cost driver is number of setups). Overhead allocated to the ordering and receiving cost pool is $200,000, and $800,000 is allocated to the machine setup cost pool. Additional information related to these pools is as follows: Cost Drivers Tables Chairs Purchase orders 30,000 10,000 number of setups 10,000 30,000 a. Determine the amount of overhead assigned to the table product line and the chairs product line using activity-based costing. b. What amount of overhead would be assigned to the tables and chairs product lines using the traditional approach,…arrow_forward?Refer to CASE 2 (Company B), What is the expected Product Margin of product Z if activity-based costing is used None of the amounts given .a O $101,250 b O $62,000 .c O $23,000 .d Oarrow_forward
- esc Chain Reaction, Inc. allocates overhead using machine hours as the allocation activity. The following information was estimated at the beginning of the year: $300,000 of Estimated Manufacturing Overhead 10,000 Estimated Machine Hours 20,000 Estimated Direct Labor Hours During the year, it took 2,000 machine hours and 6,000 direct labor hours to produce the mountain bikes. How much manufacturing overhead was allocated to the mountain bikes during the year? Click Save and Submit to save and submit. Click Save All Answers to save all answers. 1 Q A 2 W S #3 E D $ 4 R % dlo L 5 F MacBook Pro T < 6 G & Y 7 H * 00 8 U J garrow_forwardAt the beginning of the year, Jones Manufacturing Company predicts total overhead costs in the amount of $896,000. The company applies overhead using machine-hours and estimates that it will use 32,000 machine-hours during the upcoming year. REQUIRED: What amount of overhead should be applied to Job 14A if that job uses 40 machine-hours? A) $1,120 B) $1,140 C) $2,240 D) $3,360arrow_forwardMary Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed below: Maintenance 200,000.00 Material handling 32,000.00 Setups 100,000.00 Inspection 120,000.00 Currently, overhead is applied using a predetermined overhead rate, based on 80% of direct labor. The company has been asked to submit a bid for a proposed job. The plant manager feels that getting this job would result in new business in future years. Bids are based on full manufacturing cost plus 20 percent. Estimates for the proposed job are as follows: Direct materials 6,000.00 Direct labor (1k hours) 10,000.00 No. of materials moves 12.00 No. of inspections 10.00 No. of setups 2.00 No. of machine hours 500.00 In the past, full manufacturing cost has been calculated using normal costing. The plant manager has heard of a new way of applying overhead that…arrow_forward
- Mary Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed below: Maintenance 200,000.00 Material handling 32,000.00 Setups 100,000.00 Inspection 120,000.00 Currently, overhead is applied using a predetermined overhead rate, based on 80% of direct labor. The company has been asked to submit a bid for a proposed job. The plant manager feels that getting this job would result in new business in future years. Bids are based on full manufacturing cost plus 20 percent. Estimates for the proposed job are as follows: Direct materials 6,000.00 Direct labor (1k hours) 10,000.00 No. of materials moves 12.00 No. of inspections 10.00 No. of setups 2.00 No. of machine hours 500.00 In the past, full manufacturing cost has been calculated using normal costing. The plant manager has heard of a new way of applying overhead that…arrow_forwardMary Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed below: Maintenance 200,000.00 Material handling 32,000.00 Setups 100,000.00 Inspection 120,000.00 Currently, overhead is applied using a predetermined overhead rate, based on 80% of direct labor. The company has been asked to submit a bid for a proposed job. The plant manager feels that getting this job would result in new business in future years. Bids are based on full manufacturing cost plus 20 percent. Estimates for the proposed job are as follows: Direct materials 6,000.00 Direct labor (1k hours) 10,000.00 No. of materials moves 12.00 No. of inspections 10.00 No. of setups 2.00 No. of machine hours 500.00 In the past, full manufacturing cost has been calculated using normal costing. The plant manager has heard of a new way of applying overhead that…arrow_forwardMary Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed below: Maintenance 200,000.00 Material handling 32,000.00 Setups 100,000.00 Inspection 120,000.00 Currently, overhead is applied using a predetermined overhead rate, based on 80% of direct labor. The company has been asked to submit a bid for a proposed job. The plant manager feels that getting this job would result in new business in future years. Bids are based on full manufacturing cost plus 20 percent. Estimates for the proposed job are as follows: Direct materials 6,000.00 Direct labor (1k hours) 10,000.00 No. of materials moves 12.00 No. of inspections 10.00 No. of setups 2.00 No. of machine hours 500.00 In the past, full manufacturing cost has been calculated using normal costing. The plant manager has heard of a new way of applying overhead that…arrow_forward
- Mary Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed below: Maintenance 200,000.00 Material handling 32,000.00 Setups 100,000.00 Inspection 120,000.00 Currently, overhead is applied using a predetermined overhead rate, based on 80% of direct labor. The company has been asked to submit a bid for a proposed job. The plant manager feels that getting this job would result in new business in future years. Bids are based on full manufacturing cost plus 20 percent. Estimates for the proposed job are as follows: Direct materials 6,000.00 Direct labor (1k hours) 10,000.00 No. of materials moves 12.00 No. of inspections 10.00 No. of setups 2.00 No. of machine hours 500.00 In the past, full manufacturing cost has been calculated using normal costing. The plant manager has heard of a new way of applying overhead that…arrow_forwardSPL Enterprises assigns overhead based on number of machine hours. For the upcoming year, they plan to use a total of 250,000 machine hours and 50,000 direct labor hours. Total overhead cost is expected to be $500,000. The predetermined overhead ratearrow_forwardCanfield Technical School allocates administrative costs to its respective departments based on the number of students enrolled, while maintenance and utility costs are allocated based on the square footage of each department's classroom. Based on the information below, what is the total amount of administrative cost to the Accounting Department (rounded to the nearest dollar) if administrative costs for the school were $56,000, maintenance fees were $12,600, and utilities were $6,300? Department Electrical Students 126 Classroom Square Feet 10,300 Welding 73 12,300 Accounting 53 8,300 Carpentry 43 6,300 Total 295 37,200arrow_forward
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College