The processing times of four jobs are given as follows: Job Processing time (minutes) A 10 B 30 C 16 D 24 Assume the jobs arrived in alphabetical order of the job name and no other job arrives in the next 70 minutes. What is the average flow time in minutes if the jobs are processed in shortest processing time (SOP) order? Group of answer choices 166 41.5 38 20.5

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
Question 32 

The processing times of four jobs are given as follows:

Job

Processing time (minutes)

A

10

B

30

C

16

D

24

Assume the jobs arrived in alphabetical order of the job name and no other job arrives in the next 70 minutes. What is the average flow time in minutes if the jobs are processed in shortest processing time (SOP) order?

Group of answer choices
166
41.5
38
20.5
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Production Plant
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,