a. Determine the expected activity completion times b. Identify the critical path.  c. If activity B were delayed by 2 days, how long can activity G be delayed without delaying the whole project?

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%

a. Determine the expected activity completion times

b. Identify the critical path. 

c. If activity B were delayed by 2 days, how long can activity G be delayed without delaying the whole project?

Activity
tm te
to
tm
Immediate Predecessor/s
А
1
1
9
В
4
7
C
5
A
1
2
D
2
9
A
E
4
A
F
1
2
A
G
8
10
B
H
3
4
11
С, D, E, F
Transcribed Image Text:Activity tm te to tm Immediate Predecessor/s А 1 1 9 В 4 7 C 5 A 1 2 D 2 9 A E 4 A F 1 2 A G 8 10 B H 3 4 11 С, D, E, F
Expert Solution
Step 1 - Introduction

Given data is

Management homework question answer, step 1, image 1

Step 2 - Calculating expected completion time

The formula for calculating expected completion time is

Expected completion time=to+4tm+tp/6

Here,

to = Optimistic time

tm = Most likely time

tp = Pessimistic time

The table below shows the expected completion time for each activity.

Management homework question answer, step 2, image 1

Step 3 - Creating flow diagram and possible path identification

The flow diagram for the project data given in the question is shown below.

Management homework question answer, step 3, image 1

The activity with its expected completion time is shown in the above flow diagram.

The table below shows all the possible paths and their duration to complete the project.

Path Completion duration in days
A-C-H 15
A-D-H 13
A-E-H 14
A-F-H 12

 

steps

Step by step

Solved in 5 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON