please solve I edited the previus question An 15-MW wind farm (15 wind turbines, 1 MW) was installed in NEOM region. If the installed costs were 1.5 million $/MW, FCR = 5%, if the annual energy produced is 30000 MWh/year, AOM = 10 $/MWh. Calculate the COE in $/MWh? O a. 47.5 $/MWh O c. 33.4 $/MWh O d. 27.9 $/MWh Clear my choice If the wind farm owners sells electricity to utility company at 80 $/MWh. The complex Payback period for the project is: O a. 33 years O b. 11 years Q. c. 5 years O d. 23 years Clear my choice The capacity factor of the wind farm is: O b. 23% d. 15% Ć Clear my choice Show Transcribed Text

University Physics Volume 1
18th Edition
ISBN:9781938168277
Author:William Moebs, Samuel J. Ling, Jeff Sanny
Publisher:William Moebs, Samuel J. Ling, Jeff Sanny
Chapter1: Units And Measurement
Section: Chapter Questions
Problem 56P: Estimates and Fermi Calculations Assuming the human body is made primarily of water, estimate the...
icon
Related questions
Question

Please give right answer 

And solve step by step thanks

please solve I edited the previus question
An 15-MW wind farm (15 wind turbines, 1 MW) was installed in NEOM region. If the
installed costs were 1.5 million $/MW, FCR = 5%, if the annual energy produced is
30000 MWh/year, AOM= 10 $/MWh. Calculate the COE in $/MWh?
O a. 47.5 $/MWh
0 19
33.4 $/MWh
d. 27.9 $/MWh
Clear my choice
O c.
If the wind farm owners sells electricity to utility company at 80 $/MWh. The
complex Payback period for the project is:
O a. 33 years
b. 11 years
c. 5 years
d. 23 years
Clear my choice
The capacity factor of the wind farm is:
O b. 23%
O d. 15%
Ć
Clear my choice
Show Transcribed Text
Transcribed Image Text:please solve I edited the previus question An 15-MW wind farm (15 wind turbines, 1 MW) was installed in NEOM region. If the installed costs were 1.5 million $/MW, FCR = 5%, if the annual energy produced is 30000 MWh/year, AOM= 10 $/MWh. Calculate the COE in $/MWh? O a. 47.5 $/MWh 0 19 33.4 $/MWh d. 27.9 $/MWh Clear my choice O c. If the wind farm owners sells electricity to utility company at 80 $/MWh. The complex Payback period for the project is: O a. 33 years b. 11 years c. 5 years d. 23 years Clear my choice The capacity factor of the wind farm is: O b. 23% O d. 15% Ć Clear my choice Show Transcribed Text
Expert Solution
steps

Step by step

Solved in 5 steps with 3 images

Blurred answer
Knowledge Booster
Chemical Thermodynamics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, physics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
University Physics Volume 1
University Physics Volume 1
Physics
ISBN:
9781938168277
Author:
William Moebs, Samuel J. Ling, Jeff Sanny
Publisher:
OpenStax - Rice University