ABC Ltd Company is in the process of preparing a budget for launching a new product. The following table provides the associated activities and their durations. Activity Predecessors Duration (wks) A: forecast sales volume - 10 B: study competitive market - 7 C: design item and facilities A 5 D: prepare production schedule C 3 E: estimate cost of production D 2 F: set sales price B, E 1 G: prepare budget E, F 14
ABC Ltd Company is in the process of preparing a budget for launching a new product. The following table provides the associated activities and their durations. Activity Predecessors Duration (wks) A:
Construct the precedence table, and hence draw the network for the project