What are the values of the slack for activities B and F?
Q: Define the term Slack-Time?
A: Project management can be termed as the application of knowledge, techniques, tools, skills, and…
Q: a. Which activity has the largest slack?
A: THE ANSWER IS AS BELOW:
Q: If an activity has a total duration of 8 days and the schedule is 50% complete, how many days until…
A:
Q: Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic (tp) time…
A: First, there is a need to determine the expected time of each activity. Expected Time =(to+4tm+tp)6
Q: 11-17 The following are the activity times for the project in Problem 11-16. Find the earliest,…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: What is a work breakdown structure, and how is it useful for project planning?
A: Work breakdown structure is the term in project management that enables especially for large and…
Q: Describe the meaning of slack, and discuss how it can be determined.
A: Project management is the application of processes, methods, skills, knowledge and experience in…
Q: snip
A: If task A is an immediate predecessor of task B, task A must be completed first before task B.
Q: d. How long the program is expected to finish? e. Determine the slack time for each activity using…
A: given,
Q: Can activities in a work breakdown structure wbs be planned concurrently? Why or why not
A: WBS is a tool that provides guidance for schedule development and control by providing detailed…
Q: Identify the many types of real-time scheduling methods available to the project team.
A: Scheduling: Scheduling is very essential to every project and it helps to plan the…
Q: Critically discuss the concept of Project Management in relation to how it may contribute to the…
A: Maintaining or managing a project generally comprises recognizing the needs, setting clear and…
Q: Identify the term being described for each of the following: (a). A sequence of activities in a…
A: a) Path is said to be the sequence of activities in a project. b) Critical path is the longest time…
Q: Based on the activity time estimates, the expected times for each of the activities are (round…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1. Dayagsky Construction Firm, Inc. will soon begin to work on a building for US tea that was…
A: From the given data: Activity code Estimated time A-B 2 B-E 8 B-C 1 C-E 2 C-D 2 D-E…
Q: d. How much slack is in Activity C? What does this mean? e. How much slack is in Activity E?
A: The critical task is the task that performs the operations on the critical path of the project that…
Q: What are the problems associated with using flexible schedules?
A: Flexible work arrangements is a broad term that encompasses a wide range of scenarios. If your…
Q: What is the optimal plan for expediting some activities so as to minimize the total cost of…
A: Cost optimization in the time of advanced business implies that associations utilize a blend of IT…
Q: e of it to p
A: The schedule, resources required, and the actuality of the project's delivery are all determined by…
Q: Sushant and his team of frenco Ltd. Want to ascertain the expected time and variance for an Activity…
A: Given : Optimistic Time (a) - 2 weeks Pessimistic time (b) - 8 weeks Most likely time (m) - 3 weeks…
Q: (d) Suppose you want to shorten the completion time as much as possible and you have the option of…
A: Activity Activity time Immediate Predecessor(s) A 4 - B 2 A C 4 A D 3 C E 5 B,D F 6 D…
Q: Activity times with the greatest uncertainty are activities D, E, and H. Describe conceptually how…
A: Activity times with the greatest level of uncertainties are D,E and H. This could be modeled in…
Q: How many activities have non-zero free slack? Choose. How many activities have non-zero total slack,…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: What is the definition of a assignment matrix in project management?
A: A Responsibility Assignment Matrix establishes the extent to which numerous organisations, persons,…
Q: The difference between the late and early start time for an activity is?
A: Answer given below:
Q: How do we calculate slack?
A:
Q: The achievement of the objectives of a project will be possible only by applying the appropriate…
A: Let’s get to know the difference between the two by getting to know the meaning of the scheduling…
Q: Describe the main considerations to keep in mind when developing a scheduling scheme in project…
A: Project scheduling is the process in which all the project activities and deliverables are listed in…
Q: NSTRUCTIONS: Draw the AON network for Exercise 14 (pg ASSIGNMENT 200 & 201). Complete the forward…
A: Project management is the process of overseeing a team's activity to complete all project objectives…
Q: Identify the term being described for each of the following: b. The longest time sequence of…
A: b. The critical path is the longest time sequence of activities in a project.
Q: Identify the term being described for each of the following: g. Shortening an activity by allocating…
A: The term used to determine shortening of an activity by allocating additional resources is called…
Q: what is the difference between work package and wbs?
A: Introduction of work package A work package is a group of related tasks within a project. Because…
Q: Consider the network presented in the following table. Calculate the slack for activity D. (Enter…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: why do you think scheduling issues often cause great concern for project managers?
A: Project scheduling begins with identifying and estimating the durations for different tasks in the…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: The question is related to Crashing. The cost slope will be calculated for each activity with the…
Q: What qualities does a project need to be able to use critical path scheduling?
A: Critical path scheduling is an invaluable tool that project managers have at their disposal. Without…
Q: A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the…
A: Programme Evaluation and Review Technique(PERT) is a probabilistic technique, where an activity time…
Q: What does it mean for a path to have three weeks of slack? Does each activity necessarily have three…
A: Slack on the project path is important to the managers. It is the amount of time when the activities…
Q: Describe the meaning of slack, and discuss bow it can be determined.
A: Project management is the management in which different types of skills and knowledge are used to…
Q: What are Project Scheduling Models, and how are they defined?
A: Scheduling is the process of arranging the production activities in order so that the complete…
Q: Slack time for each of the activities is? (Activity A-G)
A: Find the given details below: Given Details: Activity Immediate Predecessor(s) Time (days) A…
Q: Describe the various purposes of using project scheduling?
A: Project management scheduling contains a list of a project related activities and deliverables,…
Q: An activity has an optimistic time estimate of 2 days, a most likely estimate of 4 days, and a…
A:
Step by step
Solved in 2 steps with 1 images
- Instructions ASSIGNMENT PROJECT SCENARIO: You are married and you are the father or mother of a family of five with kids ages 10, 13 and 15) and a dog. The family has decided to take a camping trip when the children are out of school for the summer. The planned family camping trip is the project you will use to complete this assignment. INSTRUCTIONS: Create a Responsibility Matrix for no less than seven activities to be addressed in preparation for the family camping trip. Every member of the family must be assigned primary responsibility to complete at least or more activities for the project. Also, decide whether the dog will go on the camping trip with the family or whether arrangements will be made for someone to care for the dog while the family is away. Based on your decision regarding the dog, you must include at least one activity associated with the dog as part of the project responsibility matrix. Within the matrix, use "R" to indicate which individual has primary…You are given the following data for an activity: ES = 10 EF = 15 LS = 16 Which of the following can you determine from this data? A. The activity's float and duration B. Only the activity float C. Only the activity duration D. Neither the activity's float nor its duration18 Select the correct answer. Paul is the CEO of a mid-sized IT firm. Three weeks ago, he started a new project in his company. Soon after, Paul planned, scheduled, and assigned necessary tasks to his project team members. This week, the employees have started performing the tasks according to the instructions given to them on a trial. Which phase in the task lifecycle would Paul carry out next? OA. planning OB. reporting tracking testing OE. organizing Reset Next served. 99+
- If a task had a cost variance (CV) = 150 and a schedule variance (SV) = -150, how would that be interpreted? Over budget, ahead of schedule Under budget, ahead of schedule Over budget, behind schedule Under budget, behind schedule On budget, on schedule Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Critical Path Method is generally used for project planning in constructions projects. Which among the following is a characteristic of CPM It is an activity oriented technique b. Requires three time estimates Oc. It is used for non-repetitive projects d. It is a Probabilistic modelSimplifying the ABC System: DBC Electan Company produces two types of printers. The company uses ABC, and all activity drivers are duration drivers. Electan Company is considering using DBC and has gathered the following data to help with its decision. A. Activities with duration drivers: Activities Products Changeover Assembly Testing Rework Total Hours Printer A 1,000 12,000 8,000 8,000 25,000 Printer B 4,000 8,000 12,000 12,000 25,000 Total hours 5,000 20,000 20,000 20,000 50,000 B. Activities with consumption ratios and costs: Activities Products Changeover Assembly Testing Rework CostAssignment Printer A 0.20 0.60 0.40 0.80 $155,000 Printer B 0.80 0.40 0.60 0.20 $155,000 Activity costs $75,000 $120,000 $60,000 $55,000 $310,000 C. Products with cycle time and practical capacity: Products Cycle Time PracticalCapacity…
- Suppose that a task in a project has the following time estimates: to=optimistic completion time=9 weeks tm=most likely completion time=17 weeks tp=pessimistic completion time=21 weeks Compute the expected task completion time. The expected task completion time is _________ weeks. (Enter your response rounded to one decimal place.)how can the below control problem be resolve in a business and how does this control problem affect the business MISSING GUARANTED DEADLINE AND LATE DELIVERY9:36 Assignment Details Introduction to Business (BUSG-129-WJ1 CRN: 23348) Description After watching the following 4 UTube videos, students are to discuss the keys points from each of these 4 videos: 1. What is a stock market index? 2. Stocks, Bonds, Funds - What's the difference? 3. What are dividends? 4. What is a 401K? W VES Dashboard 56 ا... Stock Market Index | by Wal... 3 CODIGO T View Discussion 000 000 Calendar 7 To Do NA Notifications Inbox
- (1) Suppose a project manager is reviewing the project management plan, the work performance data, and the project schedule. She is getting ready to do next? Work the project plan. Plan the project schedule. Start Control Schedule. Create the WBS. (2) During the Control Schedule process, what is one of the most common outputs? Stakeholder meeting Team meeting Vacation request Change requestLimbo Technologies has embarked on another project that has an estimated completion time of 40 weeks and a standard deviation of 5 weeks. It is estimated that the project completion time is normally distributed. i)What is the probability of finishing the project in 38 weeks or less? ii)The due date for the project is set so that there is a 90% chance that it will finish by this date. What is the due duration? ACTIVITY PREDECESSOR NORMAL TIME (WEEKS) CRASH TIME (WEEKS) NORMAL COST ($) CRASH COST ($) A - 4 2 1000 1600 B - 6 3 3000 3500 C A 3 1 2500 3000 D A,B 6 5 1500 1850 E D 4 2 3500 4200 F C 4 3 2250 3000 G D 3 2 1900 2500 H F,G,E 2 1 400 500Suppose that a task in a project has the following time estimates: to=optimistic completion time=10 weeks tm=most likely completion time=17 weeks tp=pessimistic completion time=19 weeks Compute the expected task variance. The task expected task variance is _____ weeks. (Enter your response rounded to two decimal places.)