What are the interest tax shields from the project? What is their present value? d. Show that the APV of Alcatel-Lucent's project matches the value computed using the WACC method Make sure to provide in TEXT. No to SNIP AND HANDRWRITING. MAKE SURE IT IS CORRECT ALSO. NOT FROM CHAT GOT. Clean format. Thank you. I’ll rate you uplike

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter11: Capital Budgeting And Risk
Section: Chapter Questions
Problem 6P
icon
Related questions
Question
c. What are the interest tax shields from the project? What is their present value? d. Show that the APV of Alcatel-Lucent's project matches the value computed using the WACC method Make sure to provide in TEXT. No to SNIP AND HANDRWRITING. MAKE SURE IT IS CORRECT ALSO. NOT FROM CHAT GOT. Clean format. Thank you. I’ll rate you uplike
Suppose Alcatel-Lucent has an equity cost of capital of
10.6%,
market capitalization of
$10.65
billion, and an enterprise value of
$15
billion. Assume that Alcatel-Lucent's debt cost of capital is
7.1%,
its marginal tax rate is
37%,
the WACC is
8.8232%,
and it maintains a constant debt-equity ratio. The firm has a project with average risk. The expected free cash flow,
levered value, and debt capacity are as follows:
(Click on the following icon in order to copy its contents into a spreadsheet.)
2
95
68.00
19.72
Year
FCF ($ million)
✓
D=dxV²
0
-100
178.99
51.91
1
45
149.78
43.44
Thus, the NPV of the project calculated using the WACC method is
$178.99 million-$100 million=$78.99 million.
3
74
0.00
0.00
Transcribed Image Text:Suppose Alcatel-Lucent has an equity cost of capital of 10.6%, market capitalization of $10.65 billion, and an enterprise value of $15 billion. Assume that Alcatel-Lucent's debt cost of capital is 7.1%, its marginal tax rate is 37%, the WACC is 8.8232%, and it maintains a constant debt-equity ratio. The firm has a project with average risk. The expected free cash flow, levered value, and debt capacity are as follows: (Click on the following icon in order to copy its contents into a spreadsheet.) 2 95 68.00 19.72 Year FCF ($ million) ✓ D=dxV² 0 -100 178.99 51.91 1 45 149.78 43.44 Thus, the NPV of the project calculated using the WACC method is $178.99 million-$100 million=$78.99 million. 3 74 0.00 0.00
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Economic Value Added
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT