If the first activity in a given project is D which precedes A, B. And activity A precedes H,G. And activity B precedes C, E, F. Activities C and E,G precede M and activity H precedes I. And activities M,I precede activity J, which represents the last activity in the project, and the completion times for each activity are D=5, A = 3, B=3, H=2 G=5, C=4 E= 2 F=8, M J=2 . 1=3, Find 1/critical path Method 2/ Early start time 3/ Early finish time 4/latest start time 5/latest finish time 6/float time 7/ free float time the project network diagram?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
If the first activity in a given project is D which
precedes A, B. And activity A precedes H,G. And
activity B precedes C,E, F. Activities C and E,G
precede M and activity H precedes I. And activities
M,I precede activity J, which represents the last
activity in the project, and the completion times
for each activity are D=5, A = 3, B=3, H=2 G=5, C=4
E= 2 F=8, M J=2 . 1-3, Find
1/critical path Method 2/ Early start time
3/ Early finish time
4/latest start time
5/latest finish time
6/float time
7/ free float time
the project network diagram?
Transcribed Image Text:If the first activity in a given project is D which precedes A, B. And activity A precedes H,G. And activity B precedes C,E, F. Activities C and E,G precede M and activity H precedes I. And activities M,I precede activity J, which represents the last activity in the project, and the completion times for each activity are D=5, A = 3, B=3, H=2 G=5, C=4 E= 2 F=8, M J=2 . 1-3, Find 1/critical path Method 2/ Early start time 3/ Early finish time 4/latest start time 5/latest finish time 6/float time 7/ free float time the project network diagram?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.