a) Develop a project network for this problem. b) Determine the expected duration and variance for each activity.  c) Determine the EST, EFT, LST, LFT, and slack for each activity.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

A plant is acquiring new production machinery. Before the machinery can be fully functional, a number of activities must be performed. The activities, their precedence relationships, and their durations are shown in the following table.

 

Days

 

Activity

a

m

b

Immediate Predecessors

A

6

8

10

-

B

4

5

6

-

C

1

2

3

-

D

8

18

28

A

E

4

5

6

C

F

7

8

9

B, D, E

G

4

5

9

B, D, E

H

12

13

14

F

I

8

9

10

F

J

4

5

6

G, H

K

2

5

8

I, J

L

1

2

6

G, H

a) Develop a project network for this problem.

b) Determine the expected duration and variance for each activity. 

c) Determine the EST, EFT, LST, LFT, and slack for each activity.

d) What is the critical path and project completion time? 

e) What is the probability that the job will finish in 59 days or less?

f) What is the probability that the job will finish in 54 days or more?

g) Submit your excel file

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 9 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

) Determine the EST, EFT, LST, LFT, and slack for each activity.

d) What is the critical path and project completion time? 

e) What is the probability that the job will finish in 59 days or less?

f) What is the probability that the job will finish in 54 days or more?

Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.